How to make a Gantt chart in Excel

If you were asked to name three key components of Microsoft Excel, what would they be? Most likely, spreadsheets to input data, formulas to perform calculations and charts to create graphical representations of various data types.

I believe, every Excel user knows what a chart is and how to create it. However, one graph type remains opaque to many - the Gantt chart. This short tutorial will explain the key features of the Gantt diagram, show how to make a simple Gantt chart in Excel, where to download advanced Gantt chart templates and how to use the online Project Management Gantt Chart creator.

What is a Gantt chart?

The Gantt chart bears a name of Henry Gantt, American mechanical engineer and management consultant who invented this chart as early as in 1910s. A Gantt diagram in Excel represents projects or tasks in the form of cascading horizontal bar charts. A Gantt chart illustrates the breakdown structure of the project by showing the start and finish dates as well as various relationships between project activities, and in this way helps you track the tasks against their scheduled time or predefined milestones.
Gantt chart in Excel

How to make Gantt chart in Excel

Regrettably, Microsoft Excel does not have a built-in Gantt chart template as an option. However, you can quickly create a Gantt chart in Excel by using the bar graph functionality and a bit of formatting.

Please follow the below steps closely and you will make a simple Gantt chart in under 3 minutes. We will be using Excel 2010 for this Gantt chart example, but you can simulate Gantt diagrams in any version of Excel 2013 through Excel 365 in the same way.

1. Create a project table

You start by entering your project's data in an Excel spreadsheet. List each task is a separate row and structure your project plan by including the Start date, End date and Duration, i.e. the number of days required to complete the tasks.

Tip. Only the Start date and Duration columns are necessary for creating an Excel Gantt chart. If you have Start Dates and End Dates, you can use one of these simple formulas to calculate Duration, whichever makes more sense for you:

Duration = End Date - Start Date

Duration = End date - Start date + 1
Create a table for the Gantt chart

2. Make a standard Excel Bar chart based on Start date

You begin making your Gantt chart in Excel by setting up a usual Stacked Bar chart.

  • Select a range of your Start Dates with the column header, it's B1:B11 in our case. Be sure to select only the cells with data, and not the entire column.
  • Switch to the Insert tab > Charts group and click Bar.
  • Under the 2-D Bar section, click Stacked Bar.

Make a standard Excel Bar chart based on Start date.

As a result, you will have the following Stacked bar added to your worksheet:
The Stacked bar is added to the worksheet.

Note. Some other Gantt Chart tutorials you can find on the web recommend creating an empty bar chart first and then populating it with data as explained in the next step. But I think the above approach is better because Microsoft Excel will add one data series to the chart automatically, and in this way save you some time.

3. Add Duration data to the chart

Now you need to add one more series to your Excel Gantt chart-to-be.

  1. Right-click anywhere within the chart area and choose Select Data from the context menu.
    Right-click anywhere within the chart area and choose Select Data.The Select Data Source window will open. As you can see in the screenshot below, Start Date is already added under Legend Entries (Series). And you need to add Duration there as well.
  2. Click the Add button to select more data (Duration) you want to plot in the Gantt chart.
    Click the Add button to select more data for the Gantt chart.
  3. The Edit Series window opens and you do the following:
    • In the Series name field, type "Duration" or any other name of your choosing. Alternatively, you can place the mouse cursor into this field and click the column header in your spreadsheet, the clicked header will be added as the Series name for the Gantt chart.
    • Click the range selection icon next to the Series Values field.

    Click the range selection icon to add the Series Values.

  4. A small Edit Series window will open. Select your project Duration data by clicking on the first Duration cell (D2 in our case) and dragging the mouse down to the last duration (D11). Make sure you have not mistakenly included the header or any empty cell.
    Select your project's Duration data.
  5. Click the Collapse Dialog icon to exit this small window. This will bring you back to the previous Edit Series window with Series name and Series values filled in, where you click OK.
    The Series window with Series name and Series values fields are filled in.
  6. Now you are back at the Select Data Source window with both Start Date and Duration added under Legend Entries (Series). Simply click OK for the Duration data to be added to your Excel chart.
    Duration data is added to the Excel chart.The resulting bar chart should look similar to this:
    The resulting Excel bar chart

4. Add task descriptions to the Gantt chart

Now you need to replace the days on the left side of the chart with the list of tasks.

  1. Right-click anywhere within the chart plot area (the area with blue and orange bars) and click Select Data to bring up the Select Data Source window again.
  2. Make sure the Start Date is selected on the left pane and click the Edit button on the right pane, under Horizontal (Category) Axis Labels.
    Add task descriptions to the Gantt chart.
  3. A small Axis Label window opens and you select your tasks in the same fashion as you selected Durations in the previous step - click the range selection icon , then click on the first task in your table and drag the mouse down to the last task. Remember, the column header should not be included. When done, exit the window by clicking on the range selection icon again.
    Select the task descriptions.
  4. Click OK twice to close the open windows.
  5. Remove the chart labels block by right-clicking it and selecting Delete from the context menu.
    Remove the chart labels block.At this point your Gantt chart should have task descriptions on the left side and look something like this:
    The task descriptions are added on the left side of the Gantt chart.

5. Transform the bar graph into the Excel Gantt chart

What you have now is still a stacked bar chart. You have to add the proper formatting to make it look more like a Gantt chart. Our goal is to remove the blue bars so that only the orange parts representing the project's tasks will be visible. In technical terms, we won't really delete the blue bars, but rather make them transparent and therefore invisible.

  1. Click on any blue bar in your Gantt chart to select them all, right-click and choose Format Data Series from the context menu.
    Transform the bar graph into the Excel Gantt chart.
  2. The Format Data Series window will show up and you do the following:
    • Switch to the Fill tab and select No Fill.
    • Go to the Border Color tab and select No Line.

    Go to the Border Color tab and select No Line.

    Note. You do not need to close the dialog because you will use it again in the next step.

  3. As you have probably noticed, the tasks on your Excel Gantt chart are listed in reverse order. And now we are going to fix this.Click on the list of tasks in the left-hand part of your Gantt chart to select them. This will display the Format Axis dialog for you. Select the Categories in reverse order option under Axis Options and then click the Close button to save all the changes.
    Change the order of tasks on a Gantt chart.

    The results of the changes you have just made are:

    • Your tasks are arranged in a proper order on a Gantt chart.
    • Date markers are moved from the bottom to the top of the graph.

    Your Excel chart is starting to look like a normal Gantt chart, isn't it? For example, my Gantt diagram looks like this now:
    An intermediate Gantt chart in Excel

6. Improve the design of your Excel Gantt chart

Though your Excel Gantt chart is beginning to take shape, you can add a few more finishing touches to make it really stylish.

  1. Remove the empty space on the left side of the Gantt chart.As you remember, originally the starting date blue bars resided at the start of your Excel Gantt diagram. Now you can remove that blank white space to bring your tasks a little closer to the left vertical axis.
    • Right-click on the first Start Date in your data table, select Format Cells > General. Write down the number that you see - this is a numeric representation of the date, in my case 41730. As you probably know, Excel stores dates as numbers based on the number of days since 1-Jan-1900. Click Cancel because you don't actually want to make any changes here.
      Find the number of the first date.
    • Click on any date above the task bars in your Gantt chart. One click will select all the dates, you right click them and choose Format Axis from the context menu.
      Remove the empty space on the right side of the Gantt chart.
    • Under Axis Options, change Minimum to Fixed and type the number you recorded in the previous step.
  2. Adjust the number of dates on your Gantt chart. In the same Format Axis window that you used in the previous step, change Major unit and Minor unit to Fixed too, and then add the numbers you want for the date intervals. Typically, the shorter your project's timeframe is, the smaller numbers you use. For example, if you want to show every other date, enter 2 in the Major unit. You can see my settings in the screenshot below.

    Note. In Excel 365, Excel 2021 - 2013, there are no Auto and Fixed radio buttons, so you simply type the number in the box.

    Adjust the number of dates on the Gantt chart.

    Tip. You can play with different settings until you get the result that works best for you. Don't be afraid to do something wrong because you can always revert to the default settings by switching back to Auto in Excel 2010 and 2007, or click Reset in Excel 2013 and later.

  3. Remove excess white space between the bars. Compacting the task bars will make your Gantt graph look even better.
    • Click any of the orange bars to get them all selected, right click and select Format Data Series.
    • In the Format Data Series dialog, set Separated to 100% and Gap Width to 0% (or close to 0%).

    Remove excess white space between the bars of the Gantt chart.

    And here is the result of our efforts - a simple but nice-looking Excel Gantt chart:
    The final Excel Gantt chart

    Remember, though your Excel chart simulates a Gantt diagram very closely, it still keeps the main features of a standard Excel chart:

    Tips:

    • You can design your Excel Gant chart in different ways by changing the fill color, border color, shadow and even applying the 3-D format. All these options are available in the Format Data Series window (right-click the bars in the chart area and select Format Data Series from the context menu).
      Design your Excel Gant chart in different ways.
    • When you have created an awesome design, it might be a good idea to save your Excel Gantt chart as a template for future use. To do this, click the chart, switch to the Design tab on the ribbon and click Save as Template.

Excel Gantt chart templates

As you see, it's not a big problem to build a simple Gantt chart in Excel. But what if you want a more sophisticated Gantt diagram with percent-complete shading for each task and a vertical Milestone or Checkpoint line? Of course, if you are one of those rare and mysterious creatures whom we respectively call "Excel gurus", you can try to make such a graph on your own, with the help of this article: Advanced Gantt Charts in Microsoft Excel.

However, a faster and more stress-free way would be using an Excel Gantt chart template. Below you will find a quick overview of several project management Gantt chart templates for different versions of Microsoft Excel.

Gantt chart template for Microsoft Excel

This Excel Gantt chart template, called Gantt Project Planner, is purposed to track your project by different activities such as Plan Start and Actual Start, Plan Duration and Actual Duration as well as Percent Complete.

In Excel 2013 - 2021, just go to File > New and type "Gantt" in the Search box. If you cannot find it there, you can download it from Microsoft's web-site - Gantt Project Planner template. This template requires no learning curve at all, simply click on it and it's ready for use.
Gantt chart template for Excel from Microsoft

Online Gantt chart template

This is an Interactive Online Gantt Chart Creator from smartsheet.com. As well as the previous Gantt chart template, this one is fast and easy-to-use. They offer 30 days free trial, so you can sign with your Google account here and start making your first Excel Gantt diagram online straight away.

The process is very straightforward, you enter your project details in the left-hand table, and as you type a Gantt Chart is being built in the right-hand part of the screen.
Interactive Online Gantt Chart Creator

Gantt chart template for Excel, Google Sheets and OpenOffice Calc

Gantt chart template from vertex42.com is a free Gantt chart template that works with Excel as well as OpenOffice Calc and Google Sheets. You work with this template in the same fashion as you do with any normal Excel spreadsheet. Simply enter the start date and duration for each task and define % in the Complete column. To change the range of dates displayed in the Gantt chart area, slide the scroll bar.
Gantt chart template from vertex42.com

And finally, one more Gant chart Excel template for your consideration.

Project Manager Gantt Chart template

Project Manager Gantt Chart from professionalexcel.com is also a free project management Gantt chart template for Excel that can help track your tasks against their allocated time. You can choose either the standard weekly view or daily for short term projects.

Hopefully, at least one of the above-mentioned templates is suited for your needs. If not, you can create your own Gantt chart as demonstrated in the first part of this tutorial, and then save it as an Excel template.

Now that you are familiar with the main features of the Gantt diagram, you can explore it further and create your own sophisticated Gantt charts in Excel to amaze your boss and co-workers : )

Practice workbook for download

Gantt chart example (.xlsx file)

426 comments

  1. This is a fantastic resource. Thanks you for committing the labor to create such an easy-to-follow guide.

    We have a pool of temporary staff and I used this to create a graph with their contract start and end dates so we can better visualize staffing and staffing needs.

    One thing I would like is to add just a bit of space below the bottom-most bar in the chart. How can I do that?

    Thank you, and I hope all is well with you!

  2. Super Helpful Awesome
    Thanks

  3. This is really helpful and very easy. You explanation and screenshot help a lot.

  4. This is so easy to follow! Thank you so much!

  5. Thanks so much, I tried every program available, but yours was the only one that worked with Excel.

  6. Would like to add a third date column. I would like a Start date (the date the project was created); an Actual date (date the work actually started) and then an end date. and would like to add a stacked bar chart for each of these date ranges. Is it possible and how? Thanks

  7. Thanks! very helpful!

  8. Thank you so much! Helped a lot!!

  9. Svetlana,
    I'm so proud of myself for following this guide to make an amazing GANTT chart. But ever so humbled and impressed that you were able to figure this out and create the guide that is easy to follow.
    We have a large contingent of traveler/temporary staff in our department, and my graph shows their contracts laid out beautifully. I even added 3D effects (lighting and shading) to the bars to give it some pizzazz.

    I hope you and your family are safe and secure. God Bless.

  10. Spot on. Thanks alot for the explanation.

  11. You saved a lot of my time. Great tutorial with step by step information. Much appreciated!

  12. Thank you so much. Very useful. Clear steps to follow.

  13. This was the best explanation I could have asked for. Saved my day. Thank you so much for making every effort to make it simple.

  14. Hi there,
    You showed how to get the basic Gantt chart... but what are the steps to get the progress percentage AND have the bar slowly fill up to 100% as progress continues?

    Thank you!

    • I wish to know as well. Thanks

  15. Hi Svetlana Cheusheva,

    You are such a great teacher. Thanks

    May God give you strength and bring this war to an end.

    Chijioke

  16. Thank you so much for this excellent tutorial, it was simple to follow, easy to execute. Absolute life saver. Loved it, very much appreciated.

  17. Very nice ....from Pakistan ?

  18. Waouh, You have really sorted me out here. very helpful. keep the work.

  19. Tremendous and very easy to use, thank you!

  20. Thank you so much! This was so helpful.

  21. I am using a Gantt chart to show comparative lifetimes of members of a family tree.
    Works very well although I need to reduce the the gaps between individual's data, so that I can a large family on a single chart.
    Thanks for the help.

  22. When I do this in Excel my minimum Axis defaults to 0 as opposed to selecting the lowest date as yours shows. I understand I can manually override it, but defeats the purpose of a rolling task log that can be used for years

Post a comment



Thank you for your comment!
When posting a question, please be very clear and concise. This will help us provide a quick and relevant solution to
your query. We cannot guarantee that we will answer every question, but we'll do our best :)